Alachua County has 34 road and trail projects worth $57.6 million in design, led by a $13.2 million Archer Braid Trail extension. Fifty projects are finished and five are under way.

Alachua County has 34 road, sidewalk and trail projects worth $57.6 million in design. The largest is a $13.2 million extension of the Archer Braid Trail toward Kanapaha.

The county set out the figures in its fourth-quarter roads update for the 2026 budget year, published Nov. 3. It covers the county’s 10-year Transportation Capital Improvement Program, which the county describes as a $250 million commitment by the County Commission.

Where the program stands

The county said 50 projects totaling $56.9 million have been finished since voters approved the Wild Spaces & Public Places sales tax. That work covered more than 120 lane miles of road and nine new crosswalk or signal projects.

Phase Projects Value
Completed 50 $56.9 million
Under construction 5 $11.7 million
In design (pre-construction) 34 $57.6 million

Ten of the 34 design projects were added in the last quarter, the county said.

Bar chart of Alachua County's road program by phase: $56.9 million completed across 50 projects, $11.7 million under construction across five, and $57.6 million in design across 34.
Alachua County's road program by phase. Chart by Gainesville Journal
Share this chartFacebookWhatsAppX

The biggest projects in design

The county’s release named eight design projects. Its pre-construction project sheet lists all 34. The largest is one the release left out: the Archer Braid Trail extension to Kanapaha, at $13.2 million.

The top 10 on the sheet:

Project Value
Archer Braid Trail, Kanapaha extension $13.2 million
County Road 235 (project 1) $6.1 million
County Road 235 (project 2) $4.3 million
Northeast County Road 234 $3.7 million
Holden Park Road $3.4 million
NW 98th Street $3.1 million
Kincaid Loop Trail $3.1 million
NW 39th Avenue $2.9 million
Kincaid Loop roads $2.5 million
NW 83rd Street (project 1) $2.3 million

Further down the sheet are several projects on roads Gainesville drivers use every day:

  • Archer Road four-laning, $2.2 million
  • SW 20th Avenue complete streets design, about $1.4 million
  • four NW 16th Avenue projects, about $1.7 million together
  • three more NW 83rd Street projects, $439,000, $439,000 and $422,000
  • NW 76th Boulevard, $683,000
  • NW 51st Street, $422,000
  • NW 76th Drive and West University Avenue, $334,000

The sheet prints the SW 20th Avenue design figure as “$1.4K.” We read it as $1.4 million, because that is the only value that makes the sheet’s 34 projects add up to its $57.6 million total.

The county gave no start dates for any of the design projects in this update.

What is under construction now

Five projects worth $11.7 million are being built, according to the county’s construction sheet:

  • NW 122nd Street, $4.5 million
  • two segments of Northeast County Road 1471, $3.1 million and $1.9 million
  • a $2 million avenue project
  • County Road 231, $268,000

The county’s release calls the $2 million project “Northwest 110th Avenue.” Its project sheet lists it as “NE 101st Ave.”

What was finished

The completed-projects sheet lists all 50. The two largest are NW 23rd Avenue, at $11.6 million, and NE/NW 53rd Avenue, at $8.5 million.

The county said these were finished in the last quarter:

  • NW 202nd Street, $2.8 million
  • Fort Clarke Boulevard, $2 million
  • SW 122nd Street, $1.8 million
  • SW 20th Avenue sidewalk, $1.7 million
  • the County Road 235 and Newberry Lane roundabout, $1.5 million
  • NW 39th Avenue, $688,000
  • NW 128th Road, $110,000
  • Hammock Oaks subdivision, $80,000

The release printed the NW 39th Avenue figure as “$688.” The project sheet gives $688,000.